These free 10×12 shed plans are for a 10 ft x 12 ft gable-roof storage shed: stick-framed 2×4 walls, a floor on treated skids and solid blocks, a 60-inch double door, a window, and a 6-in-12 roof. You get a complete material list, a cut list in actual lumber sizes, step-by-step instructions, and our own drawings. Every structural member is sized from a published table, and we show which one, so you or your building department can check the work.

Free printable plan (PDF). No email required.

One printable file with the materials list, cut list, key steps, and all eight diagrams on this page.

Check your local code first. Permit rules, setbacks, snow and wind loads, and frost depth are set by your city or county building department, not by this plan. Check with them before you buy materials or start building.

Front and gable elevations of the 10x12 gable shed: 144 in. long, 120 in. wide, 96 in. of siding at the walls, about 130-3/8 in. at the gable peak, with 31 x 82 in. double doors
Tap to open full size

Plain-language safety note: No engineer has reviewed this plan. The sizing comes from the 2024 International Residential Code (IRC) tables and manufacturer instructions, using the design conditions stated below. Your local building department sets the permit rules, snow and wind loads, and frost depth where you live. Confirm them before you build, and resize the framing if your loads are higher than the ones used here.

New to sheds? Our 4×8 lean-to shed plan is a smaller first build with a simpler roof. If you’re still choosing a size, see free shed plans by size.

What you’re building: the 10×12 design at a glance

We chose a gable roof (two slopes meeting at a ridge) because it sheds rain and snow in both directions, gives you headroom down the middle, and leaves space above the ceiling joists for light storage.

ItemSize
Floor (outside of framing)120 in. x 144 in. (10 ft x 12 ft)
Walls2×4 studs at 16 in. on center (gable walls 12 in.), 89-3/4 in. tall with plates
RoofGable, 6-in-12 slope; ridge runs the 12-ft length
Rafters2×6 at 16 in. on center, 12 in. eave overhangs, flush gable ends
Ceiling joists (rafter ties)2×6 at 16 in. on center, beside each rafter
Ridge2×8 ridge board
Door60 x 79-1/2 in. opening in the front wall (2 king studs and 1 jack stud each side), two 31 x 82 in. Z-frame leaves
Window24 x 24 in. rough opening in the back wall
Floor2×6 joists at 16 in. on center on three 2-ply 2×6 skids, 23/32 in. tongue-and-groove deck
Siding4×8 engineered wood panel siding, 96 in. tall on the walls

All dimensions use actual lumber sizes: 2×4 = 1-1/2 x 3-1/2 in.; 2×6 = 1-1/2 x 5-1/2 in.; 2×8 = 1-1/2 x 7-1/4 in.; 1×4 = 3/4 x 3-1/2 in.

Why the walls are 89-3/4 in. tall. The floor frame (5-1/2 in. joist + 3/4 in. deck) is 6-1/4 in. thick, so an 89-3/4 in. wall brings the siding to exactly 96 in. from the bottom of the rim to the top of the wall. One standard 8-ft siding panel covers it with no horizontal joint.

Who this plan suits: someone who has built a deck, a lean-to shed, or a few framed projects, owns a circular saw and drill, and has at least one helper for raising walls and setting the ridge. Plan on several weekends (our estimate; your pace will vary).

Tools: tape measure, speed square and framing square, chalk line, 4-ft level, circular saw (a miter saw helps), drill/driver, framing hammer, clamps, two stepladders, jigsaw, caulk gun, utility knife, tin snips, safety glasses, hearing protection, gloves, and a dust mask.

What fits in a 10×12 shed

The floor is 120 sq ft (10 ft x 12 ft), and the double-door opening is 60 in. wide, so you can roll in wider equipment than a single narrower door allows, if the item fits when you measure it. What actually fits depends on the items: mowers, bikes, a workbench along a wall, and still a walkway. Sketch your items on the 10×12 floor and check them against the 60-in. opening. For help picking among sizes, see how to choose a shed size.

Do you need a permit for a 10×12 shed?

Ask your building department before you build. Permit limits for small sheds vary by city and county, and zoning or HOA rules can apply even when no permit is needed.

A 10×12 shed has a floor area of exactly 120 square feet, which happens to be a common permit line. Two model codes set different limits:

  • The 2024 IRC, Section R105.2, exempts “one-story detached accessory structures, provided that the floor area does not exceed 200 square feet” from a building permit.
  • The 2024 International Building Code (IBC), Section 105.2, exempts “tool and storage sheds, playhouses and similar uses” where the floor area is not greater than 120 square feet. Under that model wording, a shed of exactly 120 sq ft is still inside the exemption, but local amendments change it.

Cities and counties adopt these codes and often amend them. For example, the City of Azle, Texas, amended its 2024 IBC permit exemptions, and the North Central Texas Council of Governments publishes recommended amendments that keep the 120-sq-ft line for sheds. Black Diamond, Washington, publishes a shed handout listing 200 sq ft under the IRC and 120 sq ft under the IBC.

So check with your building department before you buy materials. Ask three things: whether a 120-sq-ft shed needs a permit, how they measure the area (some may count roof overhangs), and whether there’s a height limit. Even when no building permit is needed, zoning setbacks and HOA rules still apply. And the IRC says plainly that an exemption doesn’t authorize work that violates the code.

While you’re asking, get your local ground snow load, design wind speed, and frost depth (IRC Table R301.2, filled in by each jurisdiction). The structural checks below use them. In the US, call 811 before you dig or drive ground anchors.

Site and foundation options for a 10×12 shed

Pick a level, well-drained spot with room to open both doors fully and to walk around all four sides.

Option 1: gravel pad with treated skids on solid blocks (used in this plan)

  1. Mark a pad that extends at least 12 in. past the shed on every side, about 12 ft x 14 ft. Suncast’s shed foundation guide uses the same 12-in. margin.
  2. Remove sod and level the bottom. Suncast’s guide says to excavate, usually 4 to 6 in. (check local code), fill with crushed gravel, and compact it.
  3. Set solid (not hollow) concrete blocks in three rows under the future skid lines, no more than 48 in. apart center to center, with one near each end. Use solid blocks at least 8 x 16 in., and set each block on a 16 x 16 in. (or larger) concrete pad or paver over the compacted gravel. Check soil and footing rules with your building department: IRC Table R401.4.1 presumes 2,000 psf for clay and silt and 3,000 psf for sand and gravel, and soil below 1,500 psf needs a soils investigation. The span check is in the next section.
  4. Build the skids and set them on the blocks, level and parallel.
  5. Check siding clearance. LP’s panel siding instructions require at least 6 in. between the siding and the finished grade. The siding starts at the bottom of the floor rim, which sits on top of the skids. A 2×6 skid on edge is 5-1/2 in. tall, so the blocks only need to lift it another 1/2 in.; we suggest more for airflow. Shim only with treated or composite shims.

Option 2: concrete slab (or piers)

Footings below the frost line or a concrete slab may be required in your area (IRC R403, as adopted locally) and are a good choice on sloped or soft ground. They need their own design; this plan doesn’t include slab thickness, reinforcement, or slab anchors. Ask your building department what it accepts. If you build on a slab, you’d typically fasten the floor or walls to the concrete instead of using ground anchors in soil.

Frost protection. The model 2024 IRC doesn’t require frost protection for a shed like this one. Section R403.1.4.1, Exception 1, says: “Protection of free-standing accessory structures with an area of 600 square feet (56 m2) or less, of light-frame construction, with an eave height of 10 feet (3048 mm) or less shall not be required.” This shed is a free-standing, light-frame building of 120 sq ft with its eaves under 10 ft above the ground (about 8-1/2 ft to the top of the walls if the siding starts 6 in. above grade). Your city or county can amend that rule and still require footings below the frost line, so ask your building department.

Anchoring. A 10×12 shed has a lot of wall and roof area for wind to push on. Install at least one ground anchor at each corner (four total), tied to the floor frame with the anchor maker’s cable and hardware. American Earth Anchors says the number and placement depend on shed size and soil, and shows corners plus side midpoints as one layout. Minute Man Products’ own guidelines say that where codes require anchoring to 90 mph wind standards, anchors should be at least 30 in. long with a tested holding capacity of at least 3,000 lb. Those are the manufacturer’s recommendations, not IRC values; the IRC has no ground-anchor table for sheds. Ask your building department what your wind speed requires.

Top view of the 10x12 floor frame: two 144 in. rims, ten 117 in. 2x6 joists at 16 in. on center, three 2-ply 2x6 skids, and solid blocks about 42 to 44 in. apart
Tap to open full size

How every structural member was sized

This is the part most free plans skip. Each member below lists its design condition and the table it came from, so you can check it against your local loads.

Design conditions used throughout

  • Ground snow load: up to 70 psf (the highest column in the IRC rafter and header tables); roof live load 20 psf.
  • Wind: ultimate design wind speed below 140 mph in Exposure B or below 130 mph in Exposure C. That’s the range where IRC Table R602.7.5 allows the two king studs used at the door; the uplift table (R802.11) covers up to 140 mph.
  • Lumber: No. 2 grade Douglas fir-larch, hem-fir, Southern pine, or spruce-pine-fir (check the grade stamp). Treated Southern pine for the skids and floor.
  • Building width (rafter span) 10 ft; spacing 16 in. on center.

If your loads are higher, these tables don’t cover you. Use the AWC Span Options Calculator with your values or ask your building department.

MemberSize usedDesign condition and tableAllowedThis shed
Rafters2×6 No. 2 at 16 in.IRC Table R802.4.1(7): 70 psf ground snow, 20 psf dead, ceiling not attached, L/1807 ft 5 in. (SP) to 8 ft 1 in. (DF-L), horizontal59-1/4 in. (4 ft 11-1/4 in.) wall to ridge
Rafter overhang12 in.IRC R802.7.1.1: notched cantilever24 in. max, 3-1/2 in. depth left12 in., about 3-15/16 in. left
Ridge board2×8IRC R802.3: 1 in. nominal min., at least as deep as the rafter’s cut end6-1/8 in. plumb cut needs more than a 2×67-1/4 in.
Ceiling joists (rafter ties)2×6 No. 2 at 16 in.IRC Table R802.5.1(2): attic with limited storage, 20 psf live, L/24012 ft 0 in. (SP) to 13 ft 0 in. (DF-L)113 in. (9 ft 5 in.) clear
Heel joints5-16d commonIRC Table R802.5.2(1): 5:12 row, 16 in. spacing, 12-ft span column3 / 3 / 4 / 5 nails at 20 / 30 / 50 / 70 psf5 nails
Collar ties1×4 at 16 in.IRC R802.4.2, R802.4.6: 1×4 min., 4 ft o.c. max., upper third of attic; Table R602.3(1) item 53-10d common each endBottom edge 23 in. above plates
Door header2-2×8IRC Table R602.7(1): roof and ceiling, 12-ft building width7-7 / 6-5 / 5-9 at 30 / 50 / 70 psf, 1 jack5 ft 0 in. opening
Door king studs2 each sideIRC R602.7.5 and Table R602.7.5: full-height studs at each end of a header in an exterior wall2 for a 6-ft header (footnote a: next larger span) below 140 mph Exposure B or 130 mph Exposure C5 ft 0 in. opening
Window header2-2×6Same table6-0 / 5-1 / 4-6 at 30 / 50 / 70 psf, 1 jack2 ft 0 in. opening
Wall studs2×4 at 16 in. (12 in. in gable walls)IRC Table R602.3(5): bearing wall, roof and ceiling only24 in. o.c., 10 ft height85-1/4 in. studs
Floor joists2×6 No. 2 at 16 in.IRC Table R502.3.1(2): 40 psf live, 10 psf dead, L/3609 ft 1 in. (HF) to 9 ft 9 in. (DF-L)About 55-1/2 in. clear between skids
Skids2-ply 2×6 treatedIRC Table R507.5(1) deck beams: 40 psf live, 10 psf dead, wet service included; 12-ft joist columnIRC 2021: 4 ft 4 in. (DF-L/HF/SPF), 4 ft 10 in. (SP); IRC 2024: 5 ft 3 in. (DF-L/HF/SPF), 5 ft 11 in. (SP)Blocks 42-44 in. apart (48 in. max.)
Rafter-to-wall tiesSimpson H2.5AUplift demand: IRC Table R802.11 (see “Wind and uplift”). Tie capacity: Simpson catalog p. 277 (manufacturer rating, not a code value)615 lb (SPF/HF), manufacturer rating201 lb max. at 130 mph, Exposure C (the plan’s wind range); 247 lb at 140 mph C

Notes on the table

  • Why 2×6 rafters, not 2×4: a 2×4 would pass the span check, but a birdsmouth in a 2×4 wouldn’t leave the 3-1/2 in. of depth that R802.7.1.1 requires for an overhang.
  • Why ceiling joists matter: IRC R802.2 requires continuous ties across the building so the rafters don’t push the walls apart. R802.5.2 accepts ceiling joists parallel to the rafters, in the bottom third of the rafter height, nailed per Table R802.5.2(1). That is also what lets the ridge be a plain board (R802.3) rather than an engineered beam. The rafter table assumes the ties sit at the bottom of the attic, as here.
  • Heel nails: there’s no 6:12 row, so we used the 5:12 row, which needs more nails because a lower slope pushes harder. The footnote allows 10d common nails at 1.2 times the count, rounded up (6 nails).
  • Gable-end rafters sit on gable studs, and each end of the ridge sits on a 2×4 post in the gable wall. Footnote b of Table R802.5.2(1) says heel joint connections aren’t required where the ridge is supported by a load-bearing wall, header or ridge beam, so the end pairs get no ceiling joists.
  • Header table footnote: the 30 psf column also applies where the ground snow load is under 30 psf and the roof live load is 20 psf or less.
  • Header bracing: Table R602.7(1) footnote f says the spans assume the top of the header is laterally braced by perpendicular framing; if it isn’t (for example, cripple studs bearing on the header), 2×8 and deeper header spans must be multiplied by 0.70. In this plan the door header’s top is braced by the top plate: the header sits tight under the double top plate, which carries the rafters and ceiling joists. Don’t add cripples above it without resizing the header. King studs: Table R602.7.5 sets the number of full-height (king) studs at each end of a header. The door opening is 60 in. (5 ft), and footnote a sends a span between rows to the next larger one (6 ft), which calls for 2 king studs at each end below 140 mph in Exposure B or 130 mph in Exposure C (1 is enough only at 115 mph or less in Exposure B). The window’s 2-ft opening needs 1.
  • Collar tie height: IRC R802.4.6 puts collar ties in the upper third of the attic space. With the bottom edge 23 in. above the plates, the ties are in the upper third whether you measure the attic to the underside of the rafters at the ridge (about 27-7/8 in., so the upper third starts about 18-5/8 in. up) or to the top of the ridge framing (about 34 in., about 22-11/16 in. up). That’s also as high as a 1×4 fits under the 2×8 ridge board, whose bottom is about 26-3/4 in. above the plates. The ceiling joists stay at the plates, so they are still in the bottom third (R802.5.2).
  • Floor joists have a large margin, which also covers the fact that the IRC tables assume dry lumber. Joist ends bear 1-1/2 in. on the outer skids (IRC R502.6 requires at least 1-1/2 in. on wood).
  • Skids are our adaptation. The IRC has no table for shed skids, so we used the closest one, the deck beam table, with its 12-ft joist column. That column assumes about the same floor load the center skid carries, not more. The outer skids also carry the walls and the roof, including snow, which the deck table doesn’t cover at all, so have your building department confirm the block spacing before you build. Nail the plies with two rows of 10d (3 x 0.128 in.) nails 16 in. apart along each edge (R507.5), and give each skid end at least 3 in. of bearing on its block (R507.5.1). Tell your building department that’s how the skids were checked. The 48 in. maximum block spacing passes the 2021 and 2024 editions of Table R507.5(1); we checked it against the lower 2021 values (4 ft 4 in. for DF-L/HF/SPF, 4 ft 10 in. for SP), since many places still use the 2021 IRC.
  • Floor load: 40 psf is the IRC’s live load for living areas and decks. Keep very heavy equipment near the skids, or have a pro size the floor for a tractor or workshop.

Check these judgement calls with your building department. The skids, the 6:12 heel nailing, and the gable-end rafters above use our reading of the closest IRC tables, not an engineer’s design. Show your building department this section, and follow its answer if it differs.

Section through the 10x12 shed roof: 2x6 rafters at 6 in 12, a 2x8 ridge board, 2x6 ceiling joists nailed to each rafter at the heel, a 1x4 collar tie, and 113 in. clear between walls
Tap to open full size

Material list: how much lumber a 10×12 shed needs

Quantities include a spare rafter and a few spare studs. Buy extra 2x4s if you’re new to framing.

Foundation and floor

QtyMaterial
62×6 x 12 ft treated lumber, rated for ground contact (three 2-ply skids)
12solid concrete blocks, at least 8 x 16 in. (three rows of four; see “Site and foundation”)
12concrete pads or pavers, at least 16 x 16 in. (one under each block)
—Crushed gravel for a 12 x 14 ft pad (about 2 cubic yards at 4 in. deep) and landscape fabric
22×6 x 12 ft treated lumber (rim joists)
102×6 x 10 ft treated lumber (floor joists)
423/32 in. APA Rated Sturd-I-Floor panels, span rating 24 oc, tongue-and-groove, 4 ft x 8 ft
—4 (minimum) ground anchors with cable and clamps, sized for your soil by the anchor maker

Wall framing

QtyMaterial
522×4 x 8 ft (42 studs, 4 jacks, sill and cripples, 8 gable studs and 2 ridge posts), plus a few spares
62×4 x 12 ft (front and back wall plates)
62×4 x 10 ft (gable wall plates)
12×8 x 12 ft (door header, 2 pieces)
12×6 x 8 ft (window header, 2 pieces)
—1/2 in. plywood scraps for header spacers (from the roof sheathing offcuts)

Roof framing and roofing

QtyMaterial
212×6 x 8 ft, No. 2 (20 rafters + 1 spare)
82×6 x 10 ft, No. 2 (ceiling joists)
12×8 x 12 ft, No. 2 (ridge board)
31×4 x 8 ft (8 collar ties, three per board, 1 spare)
615/32 in. or 1/2 in. APA Rated Sheathing, span rating 32/16, 4 ft x 8 ft
—Roofing underlayment for about 161 sq ft plus laps
—Drip edge, 6 pieces x 10 ft (about 51 linear ft of eaves and rakes, plus laps)
—Architectural asphalt shingles, 6 bundles (GAF says 3 bundles of Timberline HDZ cover 98.4 sq ft; this roof is about 161 sq ft, plus cutting waste), plus starter strip shingles for about 51 linear ft and hip-and-ridge cap shingles for 12 ft of ridge, per the shingle maker
—Roofing nails: IRC R905.2.5 calls for galvanized steel, stainless steel, aluminum, or copper roofing nails with a 12-gauge minimum shank and 3/8 in. minimum head, long enough to go through the sheathing (it’s thinner than 3/4 in.)
20Simpson Strong-Tie H2.5A hurricane ties, plus 200 – 0.131 x 2-1/2 in. nails (or Simpson SD9212 screws)

Siding, trim, doors, and window

QtyMaterial
154 ft x 8 ft panel siding sheets (this plan follows LP SmartSide Strand Substrate 76 Series panel instructions): 6 for the eave walls, 5 for the gable walls, 2 for the gable triangles, 2 for the door leaves
21×8 x 12 ft exterior trim (fascia)
41×6 x 8 ft exterior trim (rake boards)
151×4 x 8 ft exterior trim (8 corner boards, 4 for door rails and braces, 1 astragal, 2 window trim)
—Z-flashing, 4 pieces x 10 ft (gable joints, over the doors and window)
1clear polycarbonate sheet, 1/4 in., cut 26 x 26 in. (fixed window); or a shed window whose rough opening fits the framing
6heavy-duty exterior T-hinges or strap hinges, 2 barrel bolts for the fixed leaf, a hasp or gate latch, 2 door pulls
—1/4 in. hardware cloth, small roll (for the open rafter bays above the walls)

Fasteners and finishing (nail sizes from IRC Table R602.3(1) unless noted; IRC R304.3.1 requires hot-dipped zinc-coated galvanized, stainless, silicon bronze, or copper fasteners in preservative-treated wood)

QtyMaterial
—16d common nails (3-1/2 x 0.162 in.), hot-dip galvanized for treated lumber, for framing and heel joints
—10d common nails (3 x 0.148 in.) for rafters, collar ties, and toenailing
—10d nails (3 x 0.128 in.), hot-dip galvanized, for nailing the skid plies together (IRC R507.5)
—8d common nails (2-1/2 x 0.131 in.) for the floor deck, roof sheathing, and ceiling joist toenails; hot-dip galvanized for toenailing joists to skids
—Siding nails: 6d (0.113 in. shank) hot-dipped galvanized, long enough to go at least 1-1/2 in. into framing (LP’s minimum for 38 and 76 Series panels; not electroplated)
—1-5/8 in. exterior screws (trim, doors)
—Exterior sealant (LP calls for ASTM C920, Class 25 minimum), exterior primer and paint
The ends of neatly stacked lumber boards in a lumber yard
Photo: Mark Stebnicki / Pexels

Cut list

PartMaterialQtyLength / sizeNotes
Skid plies2×6 treated (ground contact)6144 in.Nail in pairs: 3 skids
Rim joists2×6 treated2144 in.Front and back
Floor joists2×6 treated10117 in.120 in. minus two 1-1/2 in. rims
Floor deck23/32 in. T&G panel4Full sheets; rip the last row to fitLong edges across the joists; end joints on joists
Front wall plates2×43144, 144, 137 in.Bottom, top, upper top (stops 3-1/2 in. short of each end)
Front wall studs2×41085-1/4 in.2 end, 4 common, 4 king (2 each side of the door)
Door jack studs2×4278 in.
Door header2×8263 in.Plus 1/2 in. plywood spacer, 7-1/4 x 63 in.
Back wall plates2×43144, 144, 137 in.As front
Back wall studs2×41085-1/4 in.2 end, 6 common, 2 king
Window jack studs2×4279-3/4 in.
Window header2×6227 in.Plus 1/2 in. plywood spacer, 5-1/2 x 27 in.
Window sill2×4124 in.Laid flat
Window cripples2×4254-1/4 in.Under the sill at 64 and 80 in.
Gable wall plates2×46113, 113, 120 in. per wallUpper top plate laps onto the eave walls
Gable wall studs2×42285-1/4 in.11 per wall, 12 in. on center
Gable studs2×416Long points 4-5/8, 10-5/8, 16-5/8, 22-5/8 in. (4 of each)Top cut at 6 in 12; cut to fit under the end rafters
Ridge posts2×4226-3/4 in.One per gable, centered
Rafters2×6 x 8 ft20 (+1 spare)79-5/8 in. along each edgeRidge plumb cut, birdsmouth, plumb tail
Ceiling joists2×6 x 10 ft8120 in.Clip top corners about 1-1/8 in. at each end to the roof line
Ridge board2×8 x 12 ft1144 in.
Collar ties1×4828 in.Three per 8-ft board; square-cut ends
Roof sheathing1/2 in. rated sheathing6 sheetsPer side: 48 in. course + about 32-3/8 in. rip, 144 in. longAbout 80-3/8 in. down each slope
Eave wall sidingPanel siding648 x 96 in.Full sheets; notch the top edge about 1-5/8 x 2-1/8 in. at every rafter tail (10 per wall); door opening cut out after hanging
Gable wall sidingPanel siding5Two 48 x 96 in. and one 24 x 96 in. per wallFlush with the front and back corners
Gable trianglesPanel siding2Cut to fit; one sheet per gableButt-and-flash joint at the top plate
Door leavesPanel siding231 x 82 in.
Door rails1×4428 in.
Door braces1×42Cut to fit (diagonal)Low end at each leaf’s hinge side
Astragal1×4182 in.On the active leaf
Fascia1×82144 in.Front and back rafter tails
Rake boards1×64Cut to fit (about 80 in.)Over the end rafters
Corner boards1×4896 in.Both faces of each corner

How the rafter numbers work. The run from the outside of the wall to the face of the ridge board is 60 in. (half the building) minus 3/4 in. (half the ridge) = 59-1/4 in. Add the 12 in. overhang for 71-1/4 in. of horizontal run. At 6 in 12, each inch of run is 1.118 in. along the rafter, so the rafter is about 79-5/8 in. along each edge, with the heel line about 66-1/4 in. from the ridge long point.

A worker in gloves cutting a board with a circular saw outdoors
Photo: Ron Lach / Pexels

How much does it cost to build a 10×12 shed?

Prices change often and vary by region, so we don’t print a total. To price this plan, take the material list above to a local lumber yard or home center and add up current prices for each item, including fasteners, roofing, and paint. Add delivery if you need it, and any permit fees your city or county charges.

If you want a rough sense before you go, many stores list lumber prices online; just know that those numbers may not match what’s in stock on the day you buy. We haven’t done a dated price check of this list.

Want more weekend projects? TedsWoodworking is a paid online plan collection, and the seller says it bundles over 16,000 plans. It isn’t made by Shed & Bench.

Affiliate link: we may earn a commission if you buy, at no extra cost to you. Affiliate disclosure.

Browse TedsWoodworking plans →

Step 1: Build the skids and the floor

  1. Nail each pair of 144-in. 2x6s face to face with two rows of 10d nails, 16 in. apart, along each edge (IRC R507.5). Set the three skids on edge on their blocks: one under each rim (outside faces flush with the front and back of the floor) and one centered. Level them end to end and to each other.
  2. Mark both rims for joists at 16 in. on center: one flush at each end, then centered at 16, 32, 48 … 128 in.
  3. Stand the rims on edge 120 in. apart outside to outside, set the 117-in. joists on the marks, and end-nail through the rim into each joist with three 16d common nails (IRC Table R602.3(1), item 27).
  4. Measure the diagonals and adjust until they match (both about 187-1/2 in.).
  5. Set the frame on the skids. Toenail each joist to each skid with three 8d common nails (item 22). Attach the ground anchors.
  6. Lay the deck with the long edges across the joists and the tongue-and-groove edges between joists. Stagger the end joints so they land on joists at 48 or 96 in. Nail with 8d common nails 6 in. apart at the panel edges and 12 in. at the intermediate joists (item 38). Rip the last row to fit.

Step 2: Frame the front wall with the double-door opening

  1. Cut the plates (144, 144, and 137 in.), ten 85-1/4 in. studs, two 78-in. jack studs, two 63-in. 2x8s, and a 7-1/4 x 63 in. plywood spacer.
  2. Build the header: sandwich the spacer between the 2x8s and nail with 16d common nails 16 in. apart along each edge (item 10). It’s now 3-1/2 in. thick.
  3. Mark the plates: end studs flush at each end; common studs centered at 16, 32, 112, and 128 in.; two king studs on each side of the door, from 37-1/2 to 40-1/2 in. and from 103-1/2 to 106-1/2 in. The jacks go just inside the inner kings (40-1/2 to 42 and 102 to 103-1/2 in.), leaving a 60-in. opening from 42 to 102 in.
  4. Nail the end, common, and king studs between the bottom plate and the first top plate with two 16d common end nails per joint (item 17). Face-nail each pair of kings together, and each jack to its inner king, with 16d common nails 24 in. apart (item 8).
  5. Set the header on the jacks, tight under the top plate, so the top plate braces the header’s top (Table R602.7(1) footnote f). End-nail through the inner king into each end of the header with three 16d common nails (item 12).
  6. Square the wall, raise it onto the front edge of the deck, and nail the bottom plate down with 16d common nails 16 in. apart (item 15), except inside the door opening. Brace it plumb. Leave the plate in the opening until the siding is on.
Front wall framing: 144 in. long, 89-3/4 in. tall, 85-1/4 in. studs, two king studs and one jack stud each side, a two-2x8 header, and a 60 x 79-1/2 in. door opening
Tap to open full size

Step 3: Frame the back wall with the window opening

  1. Cut the plates, ten 85-1/4 in. studs, two 79-3/4 in. jacks, two 27-in. 2×6 header pieces with a 5-1/2 x 27 in. spacer, a 24-in. flat sill, and two 54-1/4 in. cripples.
  2. Mark the plates: end studs flush; common studs centered at 16, 32, 48, 96, 112, and 128 in.; kings from 57 to 58-1/2 in. and 85-1/2 to 87 in.; jacks inside them; cripples centered at 64 and 80 in.
  3. Assemble as in Step 2. Nail the sill flat on the cripples between the jacks, so the rough opening is 24 x 24 in., with its bottom 57-1/4 in. above the deck. If you buy a shed window, frame its rough opening instead; the 2-2×6 header covers openings up to 4 ft 6 in.
  4. Raise the wall onto the back edge of the deck, nail it down, and brace it plumb.
Back wall framing: 144 in. long with a 24 x 24 in. window rough opening, two-2x6 header, flat 2x4 sill, 79-3/4 in. jacks, and 54-1/4 in. cripples
Tap to open full size

Step 4: Frame the gable walls and tie the corners

  1. For each gable wall, cut a 113-in. bottom plate, a 113-in. top plate, a 120-in. upper top plate, and eleven 85-1/4 in. studs.
  2. Lay out studs at the ends and every 12 in. measured from the front corner of the building (12, 24 … 108 in.). That puts studs under the siding joints at 48 and 96 in. and under the ridge post at 60 in.
  3. Assemble with two 16d end nails per joint, raise each wall between the eave walls, and nail the bottom plate down.
  4. Face-nail the end studs to the eave-wall end studs with 16d common nails 16 in. apart (item 9).
  5. Nail the 120-in. upper top plate on top so it laps onto the eave walls’ lower top plates, with 16d common nails 16 in. apart (item 13) and two 16d nails at each corner lap (item 18).
  6. Check that the walls are plumb and the top is square (diagonals within about 1/4 in.), then brace them.
Gable wall and gable-end framing: 113 in. between the eave walls, studs at 12 in. on center, gable studs under the end rafters, and a 26-3/4 in. 2x4 post under the 2x8 ridge board
Tap to open full size

Step 5: Cut a pattern rafter and set the ridge

  1. Mark the pattern. On a straight 2×6, mark a 6-in-12 plumb line at the top end (ridge cut). Measure 66-1/4 in. along the top edge and draw the heel plumb line. Draw the birdsmouth: a 3-1/2 in. level seat and a plumb cut about 1-3/4 in. deep. Measure another 13-3/8 in. along the top edge and mark the plumb tail cut.
  2. Test it. Set the pattern on the wall with a scrap of 2×8 at the center as a stand-in ridge. Check it at both ends and the middle of the shed, then trace and cut 19 more.
  3. Lay out the top plates: end rafters flush with each end, the rest centered at 16, 32 … 128 in.
  4. Raise the ridge. Toenail a 26-3/4 in. 2×4 post to the gable top plate at the center of each gable wall. With two helpers on ladders, set the 144-in. 2×8 ridge on the posts and nail it down.
  5. Set the rafters in opposing pairs so the ridge stays straight. At the ridge, use three 10d common toenails or two 16d common end nails per rafter (item 7). At the plates, toenail with two 10d common nails on one side (item 6 and its footnote, since each interior rafter gets a ceiling joist beside it; the four end rafters have no ceiling joist, so give each one a third 10d toenail on the opposite side); the ceiling joist gets its own toenails in Step 6.
Rafter pattern: 2x6 rafter 79-5/8 in. along each edge, 6-in-12 slope, birdsmouth with a 3-1/2 in. seat and 1-3/4 in. plumb cut, 12 in. overhang, 59-1/4 in. run to the ridge face
Tap to open full size

Step 6: Ceiling joists, heel nailing, collar ties, and hurricane ties

  1. Clip the ceiling joists. At each end of the eight 120-in. 2x6s, the top corner sticks up past the roof line, so cut a taper about 1-1/8 in. deep at the end, sloping back at 6 in 12. IRC R802.7.1.2 limits ceiling joist taper cuts to one-fourth of the depth (1-3/8 in. for a 2×6).
  2. Set one beside each interior rafter pair, resting on both eave-wall plates. Toenail each end to the plate with three 8d common nails (item 2).
  3. Nail the heel joints: five 16d common nails through the ceiling joist into the rafter at each end (Table R802.5.2(1); see the sizing section). Bend over any points that poke through.
  4. Collar ties: nail a 28-in. 1×4 across each interior pair, bottom edge 23 in. above the top of the plates, with three 10d common nails at each end (item 5). Measure the height on both rafters so the tie is level; its top edge should sit just under the ridge board.
  5. Hurricane ties: fasten a Simpson H2.5A at every rafter at both walls (20 total), with five 0.131 x 2-1/2 in. nails into the rafter and five into the plates. Put them on the inside face of the wall, on the side of each rafter away from its ceiling joist. Simpson’s evaluation report allows that (ICC-ES ESR-2613, Table 1, footnote 3), and it keeps the ties clear of the siding notches in Step 8.
  6. Gable studs: cut each stud to fit between the gable top plate and the end rafter (long points 4-5/8 to 22-5/8 in.), and toenail with four 8d common nails at each end (item 17).
  7. Snap a line across the rafter tails and trim any that stick out so the fascia runs straight.

Wind and uplift

Wind can lift a roof off its walls or slide a whole shed. IRC Table R802.11 lists the uplift force on each rafter-to-wall connection. For rafters at 16 in. on center, a roof pitch of 5:12 or more, and its smallest span (12 ft; this roof is 10 ft), the forces are:

Wind speed (ultimate)Exposure BExposure C
110 mph57 lb117 lb
120 mph85 lb157 lb
130 mph117 lb201 lb
140 mph150 lb247 lb

Simpson’s catalog lists an allowable uplift of 615 lb per H2.5A tie in spruce-pine-fir/hem-fir (700 lb in Douglas fir/Southern pine), far above any of these. Those are manufacturer ratings, not code values. Simpson says its SD9212 screws give the same load; ordinary deck or drywall screws are not a substitute. The two king studs at each side of the door assume wind below 140 mph in Exposure B or below 130 mph in Exposure C (IRC Table R602.7.5). Above those speeds, or in Exposure D, ask your building department.

The ground anchors also help. And LP says single nailing of its 76 Series panels meets wall bracing requirements, which is why this plan uses 76 Series.

Step 7: Roof sheathing, drip edge, and shingles

  1. Sheathing. IRC Table R503.2.1.1(1) allows a 32/16 panel to span 28 in. between supports without edge support, so 16 in. rafters are well within it. Start at the eave with full sheets flush with the tails, strength axis across the rafters, then rip the top course (about 32-3/8 in.) to meet at the ridge. Stagger end joints so they land on rafters. APA recommends a 1/8 in. gap at panel edges and ends unless the panel maker says otherwise.
  2. Nail it with 8d common nails (2-1/2 x 0.131 in.) 6 in. apart at the edges and 6 in. at every intermediate rafter (IRC Table R602.3(1), item 31). If your design wind speed is over 130 mph in Exposure B or over 110 mph in Exposure C, space the nails 4 in. apart at every rafter instead. On a roof this size, the table’s 48-in. edge and ridge zones cover the whole roof. Where your framing’s specific gravity is below 0.42, use RSRS-03 ring-shank nails (same footnotes).
  3. Fascia. Nail the 1×8 fascia to the rafter tails. The tails’ plumb cut is about 6-1/8 in. deep, so a 1×8 (7-1/4 in.) covers it.
  4. Drip edge and underlayment. IRC R905.2.8.5 requires drip edge at eaves and rakes of shingle roofs, lapped at least 2 in., extending at least 1/4 in. below the sheathing and 2 in. onto the deck, fastened at most 12 in. apart. Put the underlayment over the drip edge at the eaves and under it at the rakes. At 6 in 12, one layer of underlayment meets IRC R905.2.2; double underlayment is only required below 4 in 12.
  5. Shingles. Follow the shingle maker’s instructions. GAF’s Timberline instructions call for starter strips at the eaves and rakes, a 5-5/8 in. exposure, and four nails per shingle (also the IRC R905.2.6 minimum). Finish the ridge with hip-and-ridge cap shingles.
Roof framing section showing where the ridge board, ceiling joists, collar ties and hurricane ties go before the sheathing is installed
Tap to open full size

Step 8: Siding, gable triangles, and trim

LP’s panel instructions call for: studs at 16 in. on center at most; nails 6 in. apart at panel edges and 12 in. at intermediate studs, 3/8 in. from the edge, at least 1-1/2 in. into framing; 1/8 in. gaps at vertical joints and 3/16 in. at trim, sealed; at least 6 in. above grade and 1 in. above roofing; prime and paint all cut edges.

  1. Eave walls. Hang three 48 x 96 in. panels per wall, from the bottom of the rim to the top of the wall. On the front, the joints at 48 and 96 in. fall inside the door opening. First notch each panel: the rafters’ bottom edges pass through the inside corner of the top plate, so each rafter tail hangs about 1-3/4 in. below the top of the wall at its outside face, and about 2-1/16 in. below it at the face of the siding. Mark the rafter positions on the top edge of each panel and cut a notch about 1-5/8 in. wide and 2-1/8 in. deep at every tail (10 per wall, at 16 in. on center, including a corner notch at each end), then test-fit and trim. Seal the small gaps around the tails with exterior sealant, or cover them with the hardware cloth below.
  2. Cut the door opening. From inside, drill a hole at each corner, then cut along the jacks and the underside of the header with a jigsaw. Saw out the bottom plate in the opening. Cut the window opening the same way.
  3. Gable walls. Hang two full panels and a 24-in. rip per wall, flush with the outside of the front and back walls.
  4. Gable triangles. Cut each triangle from one sheet (three pieces: 48, 48, and 24 in. wide), with sloped tops that meet the underside of the roof sheathing. LP shows a butt-and-flash horizontal joint: a 3/8 in. minimum gap over sloped flashing with a 4-in. vertical leg, backed by framing (here, the gable top plate). Install Z-flashing on top of the lower panels before hanging the triangles.
  5. Trim. Nail 1×4 corner boards on both faces of each corner and 1×6 rake boards over the gable siding under the roof edge. LP says trim must be thick enough that the siding doesn’t stick out past it.
  6. Close the eaves. Staple 1/4 in. hardware cloth over the open spaces between rafters above the eave walls.
Eave detail for the 10x12 shed: each rafter tail drops below the top of the wall, so the eave-wall siding is notched about 1-5/8 x 2-1/8 in. at every tail
Tap to open full size

Step 9: Build the double doors and the window

  1. Cut two 31 x 82 in. leaves from siding panels.
  2. On each leaf’s inside face, screw 28-in. 1×4 rails across the top and bottom, inset 1-1/2 in. from the sides and about 4 in. from the ends. Add a diagonal 1×4 brace between the rails with its low end on the hinge side.
  3. Hang each leaf over the opening with three hinges into the king and jack studs, with about 1 in. of overlap at the outer edges, the tops 1-1/2 in. above the opening, and a 1/4 in. gap between the leaves.
  4. Screw a 1×4 astragal down the outside edge of the active leaf to cover the gap. Add barrel bolts at the top and bottom of the fixed leaf, a latch, and pulls.
  5. Window. Set the polycarbonate sheet over the opening in a bead of exterior sealant, then cover its edges with a 1×4 trim frame. Drill and fasten it the way the sheet maker specifies. Add Z-flashing over the window trim and the door head trim; LP says all openings must be properly sealed or flashed.
Double Z-frame doors, inside face: two 31 x 82 in. leaves with 28 in. 1x4 rails, diagonal braces with their low ends on the hinge sides, and three hinges per leaf
Tap to open full size

Finishing your 10×12 shed

  1. Prime and paint siding, trim, and all cut edges per the siding maker’s instructions.
  2. Seal joints between trim and siding, but leave the bottom edges of the siding open so water can drain.
  3. Storage above the ceiling joists. Lay 1/2 in. plywood across the joists for light storage only (IRC Table R802.5.1(2) covers attics with limited storage). It isn’t a loft for people.
  4. Inside: add shelves along the gable walls and hooks on the studs. A ramp at the doors helps with a mower.
  5. Re-check clearance: at least 6 in. between the siding and the ground all the way around.

Maintenance

  • Spring and fall: look for loose shingles or trim, gaps in sealant, and peeling paint.
  • After big storms: check that the shed hasn’t shifted and that the anchors and cables are tight. Minute Man Products recommends checking cable tension periodically in areas with heavy frost.
  • Keep it clear: don’t let soil, mulch, leaves, or snow pile against the siding.
  • Snow: clear unusual buildup from the ground with a roof rake.
  • Doors: tighten hinge screws and lubricate the hinges, bolts, and latch once a year.

Want a lean-to roof instead?

A 10×12 lean-to (single slope) is a different design: the tall and short walls change, the rafters span the full 10 ft, and the slope and roofing choices change with them. We haven’t drawn one at this size. If a single-slope roof suits your yard better, our lean-to shed plans walk through the same kind of rafter check at 4×8, and the method carries over if you redo every check for the longer span.

Build vs. buy a 10×12 shed

Building from this plan means you buy the items on the material list, frame it yourself, and can choose siding, roofing, and door hardware as you go. A 10×12 kit or a pre-built shed can be faster and needs fewer tools, but you’re limited to the seller’s size, materials, and options, and you still have to prepare the site, meet local permit and setback rules, and anchor the building.

Which costs less depends on the kit or pre-built shed, your local lumber prices, and your time. We don’t print a total for this plan or for kits. Price the material list locally, then compare that with a kit’s current price, what it includes, and delivery.

Want more plans to choose from?

If you want a large library of woodworking plans beyond this one, TedsWoodworking is a paid online plan collection, and the seller says it has over 16,000 plans, with step-by-step instructions, schematics, and materials lists. It isn’t made by Shed & Bench. Our review found it may suit you if you like browsing lots of project ideas and you’re comfortable judging a plan’s quality yourself. Critics report uneven plans, so read the review first, and check any plan all the way through and against your local code before you build.

Affiliate link: we may earn a commission if you buy, at no extra cost to you. TedsWoodworking is not made by Shed & Bench. Affiliate disclosure.

Get the free guide: Your First 10 Weekend Builds

Ten simple, original beginner projects you can build with a drill, a saw, and a couple of clamps, each with a materials list. Sent to your inbox. Unsubscribe anytime. Some emails include clearly labeled affiliate recommendations. See our Privacy Policy.

This form is protected by reCAPTCHA, and the Google Privacy Policy and Terms of Service apply.

Pinterest graphic: Free 10x12 Gable Shed Plans, with a line drawing of a gable shed with double doors
Save this plan to Pinterest

FAQs about 10×12 shed plans

Do I need a permit for a 10×12 shed?

Maybe. The 2024 IRC exempts one-story detached accessory structures up to 200 sq ft, but the 2024 IBC exempts storage sheds only when they’re not greater than 120 sq ft, and many cities amend these limits. A 10×12 shed is exactly 120 sq ft, so ask your building department before you build.

How much lumber do I need for a 10×12 shed?

For this plan, the 2×4 count on the material list is 52 2×4 x 8 ft (studs, jacks, sill and cripples, gable studs, and ridge posts), plus 6 2×4 x 12 ft and 6 2×4 x 10 ft plates (12 longer plates). You also need 21 2×6 x 8 ft rafters, 8 2×6 x 10 ft ceiling joists, a 2×8 ridge and header, and 18 treated 2x6s for the skids and floor, plus 4 floor panels, 6 roof sheathing panels, and 15 siding panels. Buy a few extra 2x4s if you’re new to framing. The full list is above.

What size rafters does a 10×12 shed need?

In this plan, 2×6 No. 2 rafters at 16 in. on center. IRC Table R802.4.1(7) allows them a horizontal span of at least 7 ft 5 in. at 70 psf ground snow, and this roof’s span is about 4 ft 11 in. The 2×6 also leaves enough depth at the birdsmouth for a 12 in. overhang.

Do I need ceiling joists or rafter ties on a gable shed?

Yes, unless the ridge is an engineered beam. IRC R802.2 and R802.5.2 require continuous ties across the building so the rafters don’t push the walls apart. This plan uses 2×6 ceiling joists nailed to each rafter with five 16d common nails.

Can I add a loft to a 10×12 shed?

This plan’s 2×6 ceiling joists meet IRC Table R802.5.1(2) for attics with limited storage, so you can lay plywood over them for light items. A loft for heavy storage or for people needs floor-joist sizing, more headroom, and a different design.

What’s the cheapest way to build a 10×12 shed?

Build it yourself on a gravel pad with skids instead of a slab, use a simple gable roof with asphalt shingles, and buy lumber in the lengths on the material list so there’s little waste. Prices vary by region, so price the list locally before you start.

Are paid shed plan packages better than free plans?

Not automatically. A good plan, free or paid, shows its sizes, its design loads, and a cut list that matches the steps. For how we look at one popular package, see our TedsWoodworking review, and compare sizes on our free shed plans by size page.

Is there a free PDF of these 10×12 shed plans?

Yes. Download the printable plan (PDF), no email required. It has the materials list, cut list, key steps, and diagrams.

Where can I find free shed building plans?

Start with our free shed plans by size, which links every plan we’ve drawn and compares common footprints. Each Shed & Bench plan includes a materials list, a cut list, and a printable PDF with no email required.

Sources

The IRC and IBC text was checked against ICC’s free online viewer (2024 IRC, edition IRC2024V2.0; 2024 IBC, edition IBC2024V1.0). The code links below go straight to ICC’s chapter pages.